Ring Normal D4105 13:30 HQ authority: held TSGB Control Suite · deterministic 4400 Hz / 20 Hz SCADA

Maintenance

Work orders and permits-to-work, interlocked against the live ring so nothing is ever worked while live.

Work orders
IDAssetTitlePriorityRaisedStatus
WO-0001 UK-SGT-Spare 6-monthly OLTC inspection on spare bank Routine 07 Aug
Maintenance
Open
WO-0002 MN-L2 Investigate SF6 pressure-sensor drift on Spain⇄Norway monitor Urgent 07 Aug
Condition monitoring
Open
WO-0003 Holland-TSGB Replace bearing RTD on TSGB unit 3 Routine 07 Aug
Maintenance
Open

Permits to work

A cable permit is only issued if the ring link is de-energised — otherwise it is refused.

PTW-0001 Issued
MN-L2 (Spain⇄Norway monitor)

Sensor calibration — read-only node, no isolation required

Issued to: T. Novak
Interlock clear — No live-cable interlock applies (read-only Monitor Node).
Raise work order
Request permit-to-work

A cable permit is only issued if the ring link is de-energised — otherwise it is refused.